KOTA KINABALU (Feb 19): The Malaysian Communications and Multimedia Commission (MCMC) will build 50 telecommunication towers across Sabah under the first phase of the National Fiberisation and Connectivity Plan (NFCP 1), which commenced earlier this month.

Sabah and Labuan MCMC director Roslan Mohamad said all the telecommunication towers are expected to be completed within six months.

“Edotco Malaysia Sdn Bhd (Edotco) and FGV Prodata Systems Sdn Bhd (Prodata) have been awarded the first phase of the NFCP project with the scope of supplying, preparing and installing the towers and its support, for the purpose of providing public cellular service,” he told reporters here, today.

He said the 50 telecommunication towers were in addition to the existing 516 owned by MCMC in Sabah.

According to him, Sabah is the State with the highest number of towers under the NFCP 1 project, accounting for 50 or 33 percent of the 152 towers to be installed nationwide.

Roslan said 152 telecommunication towers will be built nationwide for the NFCP 1 project covering eight States with 93 mukims, namely in Sabah (50 sites); Pahang (28 sites); Kelantan (18 sites); Johor (13 sites); Terengganu (13 sites); Kedah (10 sites); Negeri Sembilan (10 sites) and Perak (10 sites).

“NFCP 1 is one of the infrastructure-based initiatives identified in line with NFCP, which aims to broaden high quality digital connectivity at an affordable cost.

He said the aim of the project was to provide public cellular services in areas that have no or limited access to 3G and 4G coverage.

“NFCP 1 will improve the quality of broadband services by providing an average speed of 30Mbps,” he added.

http://www.theedgemarkets.com/article/50-telecommunication-towers-be-built-sabah-under-nfcp-1-project