TALIWRK (8524) TALIWORKS CORP BHD wins RM602m contract to develop package for Sungai Rasau water plant
KUALA LUMPUR (Dec 16): Taliworks Corp Bhd has won a contract from Pengurusan Air Selangor Sdn Bhd to develop a package under Phase 1 of the Sungai Rasau water treatment plant for RM602.43 million.
The contract is to design and build a water pumping station, and water pumping mains to the existing Bukit Lipat Kajang reservoirs, distribution and associated works (Package 2), the company said in a bourse filing.
“The date of the site possession shall be on Dec 29, 2021. The completion date for the works shall be on Dec 31, 2024 i.e. 36 months from the date of the possession of the site,” Taliworks said.
The Edge reported in October that as many as nine bidders submitted their bids for the construction of the 700 million litres-a-day water treatment plant, where the tender — valued at between RM1.7 billion and RM2 billion — was called back in May.
It is understood that other listed companies which bid for the project included IJM Corp Bhd, Gamuda Bhd, and Salcon Bhd, according to the report.
Shares of Taliworks settled unchanged at 85.5 sen, giving the company a market capitalisation of RM1.72 billion.
http://www.theedgemarkets.com/article/taliworks-wins-rm602m-contract-develop-package-sungai-rasau-water-plant
Singapore Investment
-
-
Quick Updates4 hours ago
-
-
-
-
-
-
Retire in Vietnam: The Complete Guide14 hours ago
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Portfolio Summary for April 20252 days ago
-
-
-
-
Portfolio (April 30, 2025)2 days ago
-
Portfolio (April 30, 2025)2 days ago
-
-
-
Month of April 20252 days ago
-
-
-
-
-
-
-
-
-
-
-
-
-
QAF #80 - 2024 Annual Report1 week ago
-
-
-
-
-
-
-
-
-
-
-
-
Gold on bullet train!2 weeks ago
-
Chinese Garden and Japanese Garden2 weeks ago
-
-
-
-
-
-
FAQ on Quantitative Investing Part 23 weeks ago
-
-
-
-
-
-
-
US/China/SG stocks all crashed?3 weeks ago
-
Investing vs. Speculating3 weeks ago
-
-
-
-
-
-
-
-
-
Mar 2025 Portfolio4 weeks ago
-
-
-
-
-
March 2025 Updates5 weeks ago
-
-
-
-
-
-
-
-
-
-
The Ultimate SG-JB Geo Arbitrage: Petrol2 months ago
-
-
-
-
-
-
ETF vs Mutual Fund: Which is Better?3 months ago
-
-
-
-
-
-
-
-
-
-
Arigato Everyone! A Decade of Blogging!4 months ago
-
Top 10 Highlights of 20244 months ago
-
-
2023 Trading Recap – $11,000 in profit!5 months ago
-
-
Union Square Residences6 months ago
-
-
-
STI ETF7 months ago
-
-
-
Unibet Casino Bonus Codes 20247 months ago
-
-
-
-
-
-
Monthly IBKR Update – June 20249 months ago
-
-
Portfolio Transactions (May 2024)10 months ago
-
-
-
-
-
Breakthroughs in portfolio :)11 months ago
-
-
-
Feb 2024 Expenditure1 year ago
-
-
-
-
-
-
-
Monthly Summary of November 20231 year ago
-
Migration of website1 year ago
-
-
-
-
-
-
-
-
-
A New Light1 year ago
-
-
-
-
-
-
2022 Thoughts, Hello 2023!2 years ago
-
Series of Defaults for Maple Finance2 years ago
-
Takeaways from “Sea Change”2 years ago
-
Greed is Coming Back2 years ago
-
-
-
-
-
-
-
-
What is Overemployment2 years ago
-
Terra Hill Condo (former Flynn Park)2 years ago
-
Alibaba VS Tencent: The Battle Royale2 years ago
-
-
-
-
-
-
-
-
-
-
-
-
-
Home
TALIWRK
TALIWRK (8524) TALIWORKS CORP BHD wins RM602m contract to develop package for Sungai Rasau water plant